Consultation on commonplace will be live for 6 weeks until 5 March.
With a further 4 weeks for the gym proposals.
Reviewing the Data
April 2023
-
May 2023
We will be reviewing the data and compiling into a report for publishing.
Consultation Report Shared
Sept 2023
-
Sept 2023
Development of Design
June 2023
-
Sept 2023
Design informed by consultation.
Review of design.
Costing exercise.
Value engineering revise the design.
Share Revised Design
Jan
-
Feb
Milestone description
Tender Design & Build Works
Dec 2023
-
Feb 2024
Award Contractor
March 2024
-
April 2024
SLC Southern Landscapes & Construction successful contractor awarded the works
Contractor Deliver Works
July 2024
-
Nov 2024
The approach will be phased, with the work starting on the nature garden area in mid-July.
The site will then be dormant throughout August so children can access the playground during the school holidays.
Contractors will then be back on site in early September to start work on the playground, with completion due for November.